North Para completed

Particulars
Owner: unknown
Designer: URS
Contractor: Bardavcol
Statistics
Type: Gravity
Purpose(s): Flood Control
Reservoir capacity: 1 m3x106
Height: 33 metres
Length: 206 metres
Volume of RCC: 50 m3x103
Total volume: 50 m3x103
Construction Dates
Start of Project: 11/06 (November 2006)
Start of RCC: 06/07 (June 2007)
End of RCC: 09/07 (September 2007)
End of Project: —/07 (— 2007)
Country: Australia
River: North Para
DMS Co-ordinates: 34˚33'47.00"S, 138˚46'16.36"E
DD Co-ordinates: -34.563057, 138.77121
Facings
Upstream
| Slope | Type |
|---|---|
| Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
| Slope | Type |
|---|---|
| RCC against formwork (GEVR/GE-RCC) [stepped face] |
Spillway
| Slope | Type |
|---|---|
| RCC against formwork (GEVR/GE-RCC) [stepped face] |
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
| 300 | 300 |
Cementitious material
| Cement (kg/m3) |
|---|
| 60 |
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|
| 160 | Low-lime flyash (ASTM Class F) |