North Para

Download PDF data sheet
North Para completed
North Para completed

Particulars

Owner: unknown

Designer: URS

Contractor: Bardavcol

Statistics

Type: Gravity

Purpose(s): Flood Control

Reservoir capacity: 1 m3x106

Height: 33 metres

Length: 206 metres

Volume of RCC: 50 m3x103

Total volume: 50 m3x103

Construction Dates

Start of Project: 11/06 (November 2006)

Start of RCC: 06/07 (June 2007)

End of RCC: 09/07 (September 2007)

End of Project: /07 ( 2007)

Country: Australia

River: North Para

DMS Co-ordinates: 34˚33'47.00"S, 138˚46'16.36"E

DD Co-ordinates: -34.563057, 138.77121

Facings

Upstream

SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)

Downstream

SlopeType
 RCC against formwork (GEVR/GE-RCC)  [stepped face]

Spillway

SlopeType
 RCC against formwork (GEVR/GE-RCC)  [stepped face]

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
60
Pozzolan (kg/m3)Pozzolan Type
160Low-lime flyash (ASTM Class F)