Ambarau
Download PDF data sheet
Ambarau completed

Statistics
Type: Hardfill
Purpose(s): Hydropower
Reservoir capacity: 6 m3x106
Height: 21 metres
Length: 255 metres
Volume of RCC: 33 m3x103
Total volume: 40 m3x103
Construction Dates
Start of Project: 11/14 (November 2014)
Start of RCC: 05/15 (May 2015)
End of RCC: —/16 (— 2016)
End of Project: —/17 (— 2017)
Country: DR Congo
River: Kibali
DMS Co-ordinates: 3˚05'05"N, 29˚34'57"E
DD Co-ordinates: 3.084722, 29.582500
Facings
Upstream
Slope | Type |
---|---|
0.75 | RCC against formwork with external geomembrane (GEVR/GE-RCC) [stepped face] |
Downstream
Slope | Type |
---|---|
0.75 | Traditional concrete against formwork |
Spillway
Slope | Type |
---|---|
0.75 | Traditional concrete against formwork |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
100 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
0 | No pozzolan used - |