Contraembalse de Moncion
Download PDF data sheet
Contraembalse de Moncion completed

Particulars
Owner: INDRHI (Instiuto Nacional de Recursos Hidráulicos de la República Dominicana)
Designer: Integral S.A
Contractor: Consorcio Agromán-Conde-Unión Fenosa
Statistics
Type: Hardfill
Purpose(s): Flood Control / Hydropower / Irrigation
Reservoir capacity: 8 m3x106
Height: 28 metres
Length: 254 metres
Volume of RCC: 130 m3x103
Total volume: 155 m3x103
Construction Dates
Start of Project: 07/95 (July 1995)
Start of RCC: 02/96 (February 1996)
End of RCC: 03/98 (March 1998)
End of Project: 06/98 (June 1998)
Country: Dominican Republic
River: Mao
DMS Co-ordinates: 19˚27'58.35"N, 71˚04'48.39"W
DD Co-ordinates: 19.466208, -71.080109
Facings
Upstream
Slope | Type |
---|---|
0.70 | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
0.67 | Traditional concrete against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork [stepped face] |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
80 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
0 | No pozzolan used - |