Peñas Blancas
Download PDF data sheet
Peñas Blancas completed

Particulars
Owner: unknown
Designer: ICE (Ing. William Porras)
Contractor: ICE (Ing. Irene Zúñiga)
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 2 m3x106
Height: 48 metres
Length: 211 metres
Volume of RCC: 120 m3x103
Total volume: 170 m3x103
Construction Dates
Start of Project: 04/00 (April 2000)
Start of RCC: 07/01 (July 2001)
End of RCC: 01/02 (January 2002)
End of Project: 07/02 (July 2002)
Facings
Upstream
| Slope | Type |
|---|---|
| Vertical | Traditional concrete against formwork |
Downstream
| Slope | Type |
|---|---|
| 0.80 | Traditional concrete against formwork [stepped face] |
Spillway
| Slope | Type |
|---|---|
| 0.80 | Reinforced conventional concrete cast after RCC placement |
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
| 300 | 300 |
Cementitious material
| Cement (kg/m3) |
|---|
| 90 |
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|
| 35 | Natural pozzolan (ASTM Class N) |