Queiles y Val

Download PDF data sheet
Queiles y Val completed
Queiles y Val completed

Particulars

Owner: unknown

Designer: unknown

Contractor: UTE Idecon S.A, Lain S.A. and Obrascon S.A.

Statistics

Type: Gravity

Purpose(s): Flood Control

Reservoir capacity: 25 m3x106

Height: 82 metres

Length: 375 metres

Volume of RCC: 480 m3x103

Total volume: 520 m3x103

Construction Dates

Start of Project: 01/93 (January 1993)

Start of RCC: 10/95 (October 1995)

End of RCC: 05/97 (May 1997)

End of Project: 12/98 (December 1998)

Country: Spain

River: Val

DMS Co-ordinates: 41˚52'34.65"N, 1˚47'12.90"W

DD Co-ordinates: 41.876293, -1.786917

Facings

Upstream

SlopeType
VerticalTraditional concrete against formwork
0.33Traditional concrete against formwork

Downstream

SlopeType
0.80Traditional concrete against precast concrete panels

Spillway

SlopeType
0.80Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
80
Pozzolan (kg/m3)Pozzolan Type
145Low-lime flyash (ASTM Class F)