Sambangalou
Download PDF data sheet
Photo coming soon

Particulars
Owner: unknown
Designer: unknown
Contractor: unknown
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: unknown
Height: 90 metres
Length: unknown
Volume of RCC: unknown
Total volume: unknown
Construction Dates
Start of Project: 07/17 (July 2017)
Start of RCC: —/22 (— 2022)
End of RCC: —/24 (— 2024)
End of Project: —/25 (— 2025)
Country: Senegal
River: Gambia
DMS Co-ordinates: 12˚23'57"N, 12˚11'48"W
DD Co-ordinates: 12.399167, -12.196667
Facings
Upstream
| Slope | Type |
|---|---|
Downstream
| Slope | Type |
|---|---|
Spillway
| Slope | Type |
|---|---|
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
Cementitious material
| Cement (kg/m3) |
|---|
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|