Xiaoxi
Download PDF data sheet
Particulars
Owner: unknown
Designer: Hunan Investigation Design & Research Institute of water Resources & Hydropower
Contractor: SinoHydro Construction Bureau NÂș3 Co. Ltd.
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 168 m3x106
Height: 47 metres
Length: 268 metres
Volume of RCC: unknown
Total volume: unknown
Construction Dates
Start of Project: —/04 (— 2004)
Start of RCC: —/05 (— 2005)
End of RCC: —/06 (— 2006)
End of Project: —/07 (— 2007)
Facings
Upstream
Slope | Type |
---|---|
Downstream
Slope | Type |
---|---|
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|