Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
Qingxi
[A]
ChinaHFurong98- /06- /07- /08- /0982166 154           
KöprüTurkeyHGöksu9807/0912/1004/12- /131094139751050V
0.60
(1)
(1)
0.80(1)0.80(12)3003008545(F)
ChuanjiangChinaChuanjiang98- /10- /11- /13- /1483              

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: China

Owner: -

Type: Thin Arch

Purpose(s): Hydropower

River: Furong

Reservoir capacity: 98 m3x106

Construction Dates

Start of Project: -/06

Start of RCC: -/06

End of RCC: -/08

End of Project: -/09

Specifications

Height: 82 metres

Length: 166 metres

Volume of RCC: -

Total volume: 154 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Qingxi completed
Qingxi completed

Full Dam Information

Details

Country: Turkey

Owner: -

Type: Gravity

Purpose(s): Hydropower

River: Göksu

Reservoir capacity: 98 m3x106

Construction Dates

Start of Project: 07/09

Start of RCC: 07/09

End of RCC: 04/12

End of Project: -/13

Specifications

Height: 109 metres

Length: 413 metres

Volume of RCC: 975 m3x103

Total volume: 1050 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
0.60Traditional concrete against formwork
Downstream
SlopeType
0.80Traditional concrete against formwork
Spillway
SlopeType
0.80Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
85
Pozzolan (kg/m3)Pozzolan Type
45Low-lime flyash (ASTM Class F)
  
Köprü completed
Köprü completed

Full Dam Information

Details

Country: China

Owner: -

Type: Gravity

Purpose(s): unknown

River: Chuanjiang

Reservoir capacity: 98 m3x106

Construction Dates

Start of Project: -/10

Start of RCC: -/10

End of RCC: -/13

End of Project: -/14

Specifications

Height: 83 metres

Length: -

Volume of RCC: -

Total volume: -

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  