Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
Burguillos del CerroSpainWRibera de los Montes312/9005/9109/9112/91241672533V(14)0.13
0.60
(14)*0.60(13)*30030080135(F)
Xibingxi
[A-G]
ChinaH WLongshanxi908/9312/9407/9510/9564932533V
0.08
(4)
(4)
0.65(3)ogee
0.65
(13)300 -
350
300 -
350
80
79
120
105
(F)
DahekouChinaApengjiang115- /93- /94- /96- /9785  33           

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: Spain

Owner: -

Type: Gravity

Purpose(s): Water Supply

River: Ribera de los Montes

Reservoir capacity: 3 m3x106

Construction Dates

Start of Project: 12/90

Start of RCC: 12/90

End of RCC: 09/91

End of Project: 12/91

Specifications

Height: 24 metres

Length: 167 metres

Volume of RCC: 25 m3x103

Total volume: 33 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalSlip-formed/extruded facing elements
Downstream
SlopeType
0.13Slip-formed/extruded facing elements  [stepped face]
0.60 
Spillway
SlopeType
0.60Reinforced concrete cast against precast units or slip-formed facing elements  [stepped face]

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
80
Pozzolan (kg/m3)Pozzolan Type
135Low-lime flyash (ASTM Class F)
  
Burguillos del Cerro completed
Burguillos del Cerro completed

Full Dam Information

Details

Country: China

Owner: -

Type: Arch-Gravity

Purpose(s): Hydropower / Water Supply

River: Longshanxi

Reservoir capacity: 9 m3x106

Construction Dates

Start of Project: 08/93

Start of RCC: 08/93

End of RCC: 07/95

End of Project: 10/95

Specifications

Height: 64 metres

Length: 93 metres

Volume of RCC: 25 m3x103

Total volume: 33 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork with external geomembrane
0.08RCC against formwork with external geomembrane
Downstream
SlopeType
0.65RCC against formwork
Spillway
SlopeType
ogeeReinforced concrete cast against precast units or slip-formed facing elements
0.65 

Placement

Layers (mm)Lifts (mm)
300  -300  -
350350

Cementitious material

Cement (kg/m3)
80
79
Pozzolan (kg/m3)Pozzolan Type
120Low-lime flyash (ASTM Class F)
105 
Xibingxi completed
Xibingxi completed

Full Dam Information

Details

Country: China

Owner: -

Type: Gravity

Purpose(s): unknown

River: Apengjiang

Reservoir capacity: 115 m3x106

Construction Dates

Start of Project: -/93

Start of RCC: -/93

End of RCC: -/96

End of Project: -/97

Specifications

Height: 85 metres

Length: -

Volume of RCC: -

Total volume: 33 m3x103

Construction Methods

Facings

Upstream
SlopeType
  
Downstream
SlopeType
  
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Photo coming soon

 