Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
ZhouningChinaHMuyangxi47- /0204/0303/0406/0473206159199V(3')0.72(3')0.70(12)30030067
50
100
92
(F)
Bear CreekUSAF WBear Creek4701/0810/0805/0906/09272926069V(1)0.80(1)*  3003007777(F)
EncisoSpainI WCidacos47- /0808/1407/1709/18103376695765V(1)0.80(1)*0.80(1)*30030060140(F)

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: China

Owner: -

Type: Gravity

Purpose(s): Hydropower

River: Muyangxi

Reservoir capacity: 47 m3x106

Construction Dates

Start of Project: -/02

Start of RCC: -/02

End of RCC: 03/04

End of Project: 06/04

Specifications

Height: 73 metres

Length: 206 metres

Volume of RCC: 159 m3x103

Total volume: 199 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
0.72RCC against formwork (GEVR/GE-RCC)
Spillway
SlopeType
0.70Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
67
50
Pozzolan (kg/m3)Pozzolan Type
100Low-lime flyash (ASTM Class F)
92 
Zhouning completed
Zhouning completed

Full Dam Information

Details

Country: USA

Owner: -

Type: Gravity

Purpose(s): Flood Control / Water Supply

River: Bear Creek

Reservoir capacity: 47 m3x106

Construction Dates

Start of Project: 01/08

Start of RCC: 01/08

End of RCC: 05/09

End of Project: 06/09

Specifications

Height: 27 metres

Length: 292 metres

Volume of RCC: 60 m3x103

Total volume: 69 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
Downstream
SlopeType
0.80Traditional concrete against formwork  [stepped face]
Spillway
SlopeType
  

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
77
Pozzolan (kg/m3)Pozzolan Type
77Low-lime flyash (ASTM Class F)
  
Bear Creek completed
Bear Creek completed

Full Dam Information

Details

Country: Spain

Owner: -

Type: Gravity

Purpose(s): Irrigation / Water Supply

River: Cidacos

Reservoir capacity: 47 m3x106

Construction Dates

Start of Project: -/08

Start of RCC: -/08

End of RCC: 07/17

End of Project: 09/18

Specifications

Height: 103 metres

Length: 376 metres

Volume of RCC: 695 m3x103

Total volume: 765 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
Downstream
SlopeType
0.80Traditional concrete against formwork  [stepped face]
Spillway
SlopeType
0.80Traditional concrete against formwork  [stepped face]

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
60
Pozzolan (kg/m3)Pozzolan Type
140Low-lime flyash (ASTM Class F)
  
Enciso completed
Enciso completed

 

Search again

Please note: only dams with known co-ordinates will appear on this map.

Your search returned no dams with known co-ordinates