Dam Search Results
- Volume
- Volume of RCC: 1100 m3x103
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
Jiangya | China | F H I N W | Loushui | 1741 | 07/95 | 10/96 | 04/99 | - /01 | 131 | 368 | 1100 | 1310 | V | (3') | 0.80 | (3)* | ogee 0.80 | (13) | 300 | 3000 | 87 64 46 | 107 96 107 | (F) | |
Kamchay | Cambodia | H | Kamchay | 718 | - /07 | - /09 | - /11 | - /12 | 112 | 568 | 1100 | V 0.30 | 0.75 | |||||||||||
El Zapotillo | Mexico | W | Verde | 910 | - /09 | 11/11 | - /21 | - /22 | 132 | 271 | 1100 | 1200 | V | (3') | 0.83 | (3)* | 0.83 | (3)* | 300 | 300 | 60 to 80 | 50 to 70 | (S) | |
Chame Shir [A-G] | Iran | F H I W | Zohreh | 2300 | - /11 | - /16 | - /22 | - /23 | 151 | 680 | 1100 | 1200 | V | 0.70 | 300 | 300 | 160 | 0 | (-) - |
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: China
Owner: -
Type: Gravity
Purpose(s): Flood Control / Hydropower / Irrigation / Navigation / Water Supply
River: Loushui
Reservoir capacity: 1741 m3x106
Construction Dates
Start of Project: 07/95
Start of RCC: 07/95
End of RCC: 04/99
End of Project: -/01
Specifications
Height: 131 metres
Length: 368 metres
Volume of RCC: 1100 m3x103
Total volume: 1310 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.80 | RCC against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
ogee | Reinforced concrete cast against precast units or slip-formed facing elements |
0.80 |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 3000 |
Cementitious material
Cement (kg/m3) |
---|
87 |
64 46 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
107 | Low-lime flyash (ASTM Class F) |
96 107 |
Details
Country: Cambodia
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Kamchay
Reservoir capacity: 718 m3x106
Construction Dates
Start of Project: -/07
Start of RCC: -/07
End of RCC: -/11
End of Project: -/12
Specifications
Height: 112 metres
Length: 568 metres
Volume of RCC: 1100 m3x103
Total volume: -
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | |
0.30 |
Downstream
Slope | Type |
---|---|
0.75 |
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
Details
Country: Mexico
Owner: -
Type: Gravity
Purpose(s): Water Supply
River: Verde
Reservoir capacity: 910 m3x106
Construction Dates
Start of Project: -/09
Start of RCC: -/09
End of RCC: -/21
End of Project: -/22
Specifications
Height: 132 metres
Length: 271 metres
Volume of RCC: 1100 m3x103
Total volume: 1200 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.83 | RCC against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
0.83 | RCC against formwork [stepped face] |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
60 to |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
50 to | Ground-granulated blast-furnace slag |
Details
Country: Iran
Owner: -
Type: Arch-Gravity
Purpose(s): Flood Control / Hydropower / Irrigation / Water Supply
River: Zohreh
Reservoir capacity: 2300 m3x106
Construction Dates
Start of Project: -/11
Start of RCC: -/11
End of RCC: -/22
End of Project: -/23
Specifications
Height: 151 metres
Length: 680 metres
Volume of RCC: 1100 m3x103
Total volume: 1200 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical |
Downstream
Slope | Type |
---|---|
0.70 |
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
160 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
0 | No pozzolan used - |
Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates