Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
UenoJapanHJinryu1903/97- /98- /0106/05120350269720V
0.30
(1)
(1)
0.84(1)0.84(1)200100077
70
33
30
(F)
WuduChinaF H I WFu57210/04- /07- /09- /1012063111511580V(3')0.75(3')0.80(3')    (F)
Xekaman 1LaosHXe Kaman312003/1205/1307/1512/161203358701065V(3')* (3')* (12)30030070130(F)

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: Japan

Owner: -

Type: Gravity

Purpose(s): Hydropower

River: Jinryu

Reservoir capacity: 19 m3x106

Construction Dates

Start of Project: 03/97

Start of RCC: 03/97

End of RCC: -/01

End of Project: 06/05

Specifications

Height: 120 metres

Length: 350 metres

Volume of RCC: 269 m3x103

Total volume: 720 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
0.30Traditional concrete against formwork
Downstream
SlopeType
0.84Traditional concrete against formwork
Spillway
SlopeType
0.84Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
2001000

Cementitious material

Cement (kg/m3)
77
70
Pozzolan (kg/m3)Pozzolan Type
33Low-lime flyash (ASTM Class F)
30 
Ueno completed
Ueno completed

Full Dam Information

Details

Country: China

Owner: -

Type: Gravity

Purpose(s): Flood Control / Hydropower / Irrigation / Water Supply

River: Fu

Reservoir capacity: 572 m3x106

Construction Dates

Start of Project: 10/04

Start of RCC: 10/04

End of RCC: -/09

End of Project: -/10

Specifications

Height: 120 metres

Length: 631 metres

Volume of RCC: 1151 m3x103

Total volume: 1580 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
0.75RCC against formwork (GEVR/GE-RCC)
Spillway
SlopeType
0.80RCC against formwork (GEVR/GE-RCC)

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
 Low-lime flyash (ASTM Class F)
  
Wudu completed
Wudu completed

Full Dam Information

Details

Country: Laos

Owner: -

Type: Gravity

Purpose(s): Hydropower

River: Xe Kaman

Reservoir capacity: 3120 m3x106

Construction Dates

Start of Project: 03/12

Start of RCC: 03/12

End of RCC: 07/15

End of Project: 12/16

Specifications

Height: 120 metres

Length: 335 metres

Volume of RCC: 870 m3x103

Total volume: 1065 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalRCC against formwork (GEVR/GE-RCC)  [stepped face]
Downstream
SlopeType
 RCC against formwork (GEVR/GE-RCC)  [stepped face]
Spillway
SlopeType
 Reinforced conventional concrete cast after RCC placement

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
70
Pozzolan (kg/m3)Pozzolan Type
130Low-lime flyash (ASTM Class F)
  
Xekaman 1 completed
Xekaman 1 completed

 

Search again

Please note: only dams with known co-ordinates will appear on this map.

Your search returned no dams with known co-ordinates