Dam Search Results
- Volume
- Volume of RCC: 60 m3x103
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
Sidi Yahya (formerly Ain Kwachia) | Morocco | I W | Khellata | 11 | 01/07 | 05/07 | 07/08 | 11/08 | 30 | 213 | 60 | 78 | 0.20 | (5) | 0.80 | (1)* | 0.80 | (1)* | 300 | 300 | 105 | 0 | (-) - | |
Bear Creek | USA | F W | Bear Creek | 47 | 01/08 | 10/08 | 05/09 | 06/09 | 27 | 292 | 60 | 69 | V | (1) | 0.80 | (1)* | 300 | 300 | 77 | 77 | (F) | |||
Balkusan | Turkey | H | Balkusan | 15 | - /09 | - /10 | - /11 | - /12 | 48 | 189 | 60 | 76 | V | (1) | 0.75 | (1)* | 0.75 | (12) | 300 | 1200 | 75 | 50 | ||
Çetintepe | Turkey | H | Robozik | 44 | 09/08 | - /11 | - /12 | - /13 | 39 | 173 | 60 | 64 | 0.10 | (1) | 0.80 | (1)* | 0.80 | (12) | 300 | 1200 | 77 | 63 | (N) |
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: Morocco
Owner: -
Type: Gravity
Purpose(s): Irrigation / Water Supply
River: Khellata
Reservoir capacity: 11 m3x106
Construction Dates
Start of Project: 01/07
Start of RCC: 01/07
End of RCC: 07/08
End of Project: 11/08
Specifications
Height: 30 metres
Length: 213 metres
Volume of RCC: 60 m3x103
Total volume: 78 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
0.20 | Traditional concrete against precast concrete panels |
Downstream
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork [stepped face] |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
105 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
0 | No pozzolan used - |
Details
Country: USA
Owner: -
Type: Gravity
Purpose(s): Flood Control / Water Supply
River: Bear Creek
Reservoir capacity: 47 m3x106
Construction Dates
Start of Project: 01/08
Start of RCC: 01/08
End of RCC: 05/09
End of Project: 06/09
Specifications
Height: 27 metres
Length: 292 metres
Volume of RCC: 60 m3x103
Total volume: 69 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
77 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
77 | Low-lime flyash (ASTM Class F) |
Details
Country: Turkey
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Balkusan
Reservoir capacity: 15 m3x106
Construction Dates
Start of Project: -/09
Start of RCC: -/09
End of RCC: -/11
End of Project: -/12
Specifications
Height: 48 metres
Length: 189 metres
Volume of RCC: 60 m3x103
Total volume: 76 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
0.75 | Traditional concrete against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
0.75 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 1200 |
Cementitious material
Cement (kg/m3) |
---|
75 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
50 | |
Details
Country: Turkey
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Robozik
Reservoir capacity: 44 m3x106
Construction Dates
Start of Project: 09/08
Start of RCC: 09/08
End of RCC: -/12
End of Project: -/13
Specifications
Height: 39 metres
Length: 173 metres
Volume of RCC: 60 m3x103
Total volume: 64 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
0.10 | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
0.80 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 1200 |
Cementitious material
Cement (kg/m3) |
---|
77 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
63 | Natural pozzolan (ASTM Class N) |
Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates