Dam Search Results
- Volume
- Volume of RCC: 912 m3x103
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
Gov. José Richa (formerly Salto Caxias) | Brazil | H | Iguaçu | 4 | 02/95 | 01/96 | 07/98 | 12/98 | 67 | 1083 | 912 | 1438 | V | (13) | 0.75 | (1)* | 0.75 | (12) | 300 | 300 | 80 | 20 | (F) |
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: Brazil
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Iguaçu
Reservoir capacity: 4 m3x106
Construction Dates
Start of Project: 02/95
Start of RCC: 02/95
End of RCC: 07/98
End of Project: 12/98
Specifications
Height: 67 metres
Length: 1083 metres
Volume of RCC: 912 m3x103
Total volume: 1438 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | Reinforced concrete cast against precast units or slip-formed facing elements |
Downstream
Slope | Type |
---|---|
0.75 | Traditional concrete against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
0.75 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
80 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
20 | Low-lime flyash (ASTM Class F) |
Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates