Dam Search Results
- Reservoir Capacity: 30 m3x106
 
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
| Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
| Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
| Guangzhou PSS- Lower dam | China | H | Liuxihe | 30 | 12/94 | 10/91 | 12/92 | 10/00 | 61 | 153 | 32 | 57 | V | (1) | 0.70 | (3)* | ogee 0.78  | (1) (1)  | 300 | 300 | 62 | 108 | (F) | |
| Helong | China | H R W | Hailanhe | 30 | 11/98 | 08/99 | 01/02 | 12/02 | 30 | 244 | 43 | 89 | V | (1) | 0.75 | (10) | ogee | (10)* | 300 | 2000 | 113 | 113 | (F) | |
| Olivenhain | USA | W | Escondido Creek | 30 | 06/01 | 02/02 | 10/02 | 07/03 | 97 | 788 | 1070 | 1140 | V | (4') | 0.80 | (3)* | 0.80 | (1)* | 300 | 300 | 74 | 121 | (F) | |
| Huizhou PSS - Lower dam | China | H | Caitouhe | 30 | - /02 | - /03 | - /05 | - /11 | 61 | 420 | 235 | 242 | ||||||||||||
| Kinta | Malaysia | W | Kinta | 30 | 01/03 | 02/04 | 03/06 | 07/06 | 90 | 792 | 952 | 975 | V | (3') | 0.80 | (3')* | 0.80 | (3')* | 300 | 300 | 100 | 100 | (F) | |
| Huizhou PSS - Upper dam | China | H | Xiaojinhe | 30 | 10/04 | 12/05 | 05/07 | - /11 | 56 | 168 | 84 | 93 | V | (1) | 0.75 | (1) | 0.70 | (1) | 300 | 300 | 64 | 125 | (F) | |
| Sông Côn 2 | Vietnam | H | Song Con | 30 | - /06 | - /07 | - /09 | - /10 | 58 | 260 | ||||||||||||||
| Longhuakou | China | Longhua | 30 | - /08 | - /09 | - /10 | - /10 | 63 | 353 | 414 | ||||||||||||||
| Hirase | Japan | F H W | Nishiki | 30 | - /10 | - /16 | - /20 | - /22 | 73 | 300 | 340 | |||||||||||||
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: China
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Liuxihe
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: 12/94
Start of RCC: 12/94
End of RCC: 12/92
End of Project: 10/00
Specifications
Height: 61 metres
Length: 153 metres
Volume of RCC: 32 m3x103
Total volume: 57 m3x103
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
| Vertical | Traditional concrete against formwork | 
Downstream
| Slope | Type | 
|---|---|
| 0.70 | RCC against formwork [stepped face] | 
Spillway
| Slope | Type | 
|---|---|
| ogee | Traditional concrete against formwork | 
| 0.78 | Traditional concrete against formwork | 
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
| 300 | 300 | 
Cementitious material
| Cement (kg/m3) | 
|---|
| 62 | 
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|
| 108 | Low-lime flyash (ASTM Class F) | 

Details
Country: China
Owner: -
Type: Gravity
Purpose(s): Hydropower / Recreation / Water Supply
River: Hailanhe
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: 11/98
Start of RCC: 11/98
End of RCC: 01/02
End of Project: 12/02
Specifications
Height: 30 metres
Length: 244 metres
Volume of RCC: 43 m3x103
Total volume: 89 m3x103
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
| Vertical | Traditional concrete against formwork | 
Downstream
| Slope | Type | 
|---|---|
| 0.75 | RCC against precast concrete blocks | 
Spillway
| Slope | Type | 
|---|---|
| ogee | RCC against precast concrete blocks [stepped face] | 
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
| 300 | 2000 | 
Cementitious material
| Cement (kg/m3) | 
|---|
| 113 | 
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|
| 113 | Low-lime flyash (ASTM Class F) | 

Details
Country: USA
Owner: -
Type: Gravity
Purpose(s): Water Supply
River: Escondido Creek
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: 06/01
Start of RCC: 06/01
End of RCC: 10/02
End of Project: 07/03
Specifications
Height: 97 metres
Length: 788 metres
Volume of RCC: 1070 m3x103
Total volume: 1140 m3x103
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
| Vertical | RCC against formwork with external geomembrane (GEVR/GE-RCC) | 
Downstream
| Slope | Type | 
|---|---|
| 0.80 | RCC against formwork [stepped face] | 
Spillway
| Slope | Type | 
|---|---|
| 0.80 | Traditional concrete against formwork [stepped face] | 
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
| 300 | 300 | 
Cementitious material
| Cement (kg/m3) | 
|---|
| 74 | 
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|
| 121 | Low-lime flyash (ASTM Class F) | 

Details
Country: China
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Caitouhe
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: -/02
Start of RCC: -/02
End of RCC: -/05
End of Project: -/11
Specifications
Height: 61 metres
Length: 420 metres
Volume of RCC: 235 m3x103
Total volume: 242 m3x103
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
Downstream
| Slope | Type | 
|---|---|
Spillway
| Slope | Type | 
|---|---|
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
Cementitious material
| Cement (kg/m3) | 
|---|
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|

Details
Country: Malaysia
Owner: -
Type: Gravity
Purpose(s): Water Supply
River: Kinta
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: 01/03
Start of RCC: 01/03
End of RCC: 03/06
End of Project: 07/06
Specifications
Height: 90 metres
Length: 792 metres
Volume of RCC: 952 m3x103
Total volume: 975 m3x103
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
| Vertical | RCC against formwork (GEVR/GE-RCC) | 
Downstream
| Slope | Type | 
|---|---|
| 0.80 | RCC against formwork (GEVR/GE-RCC) [stepped face] | 
Spillway
| Slope | Type | 
|---|---|
| 0.80 | RCC against formwork (GEVR/GE-RCC) [stepped face] | 
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
| 300 | 300 | 
Cementitious material
| Cement (kg/m3) | 
|---|
| 100 | 
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|
| 100 | Low-lime flyash (ASTM Class F) | 

Details
Country: China
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Xiaojinhe
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: 10/04
Start of RCC: 10/04
End of RCC: 05/07
End of Project: -/11
Specifications
Height: 56 metres
Length: 168 metres
Volume of RCC: 84 m3x103
Total volume: 93 m3x103
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
| Vertical | Traditional concrete against formwork | 
Downstream
| Slope | Type | 
|---|---|
| 0.75 | Traditional concrete against formwork | 
Spillway
| Slope | Type | 
|---|---|
| 0.70 | Traditional concrete against formwork | 
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
| 300 | 300 | 
Cementitious material
| Cement (kg/m3) | 
|---|
| 64 | 
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|
| 125 | Low-lime flyash (ASTM Class F) | 

Details
Country: Vietnam
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Song Con
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: -/06
Start of RCC: -/06
End of RCC: -/09
End of Project: -/10
Specifications
Height: 58 metres
Length: 260 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
Downstream
| Slope | Type | 
|---|---|
Spillway
| Slope | Type | 
|---|---|
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
Cementitious material
| Cement (kg/m3) | 
|---|
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|

Details
Country: China
Owner: -
Type: Gravity
Purpose(s): unknown
River: Longhua
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: -/08
Start of RCC: -/08
End of RCC: -/10
End of Project: -/10
Specifications
Height: 63 metres
Length: 353 metres
Volume of RCC: -
Total volume: 414 m3x103
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
Downstream
| Slope | Type | 
|---|---|
Spillway
| Slope | Type | 
|---|---|
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
Cementitious material
| Cement (kg/m3) | 
|---|
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|

Details
Country: Japan
Owner: -
Type: Gravity
Purpose(s): Flood Control / Hydropower / Water Supply
River: Nishiki
Reservoir capacity: 30 m3x106
Construction Dates
Start of Project: -/10
Start of RCC: -/10
End of RCC: -/20
End of Project: -/22
Specifications
Height: 73 metres
Length: 300 metres
Volume of RCC: -
Total volume: 340 m3x103
Construction Methods
Facings
Upstream
| Slope | Type | 
|---|---|
Downstream
| Slope | Type | 
|---|---|
Spillway
| Slope | Type | 
|---|---|
Placement
| Layers (mm) | Lifts (mm) | 
|---|---|
Cementitious material
| Cement (kg/m3) | 
|---|
| Pozzolan (kg/m3) | Pozzolan Type | 
|---|---|

Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates