Dam Search Results
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
Yongxi Nº3 | China | F H W | Dazhangxi | 68 | 05/96 | 10/97 | 10/98 | 09/99 | 87 | 198 | 170 | 255 | V | (3') | 0.73 | (10) | ogee 0.73 | (1) (1) | 280 | 3000 | 115 80 | 95 90 | (F) | |
Tongkou | China | H | Tongkouhe | 36 | 10/98 | - /02 | - /04 | - /04 | 72 | 198 | 300 | 352 | V | (1) | 1.10 | (1) | ogee | (1) | 300 | 300 | (F) | |||
Dahuashui [A] | China | H | Qingshui | 276 | 01/04 | 04/05 | 11/06 | - /07 | 135 | 198 | 550 | 670 | curve | (3') | curve | (3') | (1) | 300 | 3000 | 81 94 | 81 94 | (F) | ||
Şirnak | Turkey | H | Ortasui | 18 | - /08 | 11/09 | 08/10 | 09/10 | 67 | 198 | 157 | 231 | 0.10 | (1) | 0.80 | (1) | 0.80 | (12) | 300 | 600 | 125 | 0 | (-) - | |
Boa Fé | Brazil | H | Carrero | - /10 | - /10 | - /11 | - /11 | 26 | 198 | 32 | 58 |
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: China
Owner: -
Type: Gravity
Purpose(s): Flood Control / Hydropower / Water Supply
River: Dazhangxi
Reservoir capacity: 68 m3x106
Construction Dates
Start of Project: 05/96
Start of RCC: 05/96
End of RCC: 10/98
End of Project: 09/99
Specifications
Height: 87 metres
Length: 198 metres
Volume of RCC: 170 m3x103
Total volume: 255 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.73 | RCC against precast concrete blocks |
Spillway
Slope | Type |
---|---|
ogee | Traditional concrete against formwork |
0.73 | Traditional concrete against formwork |
Placement
Layers (mm) | Lifts (mm) |
---|---|
280 | 3000 |
Cementitious material
Cement (kg/m3) |
---|
115 |
80 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
95 | Low-lime flyash (ASTM Class F) |
90 |
Details
Country: China
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Tongkouhe
Reservoir capacity: 36 m3x106
Construction Dates
Start of Project: 10/98
Start of RCC: 10/98
End of RCC: -/04
End of Project: -/04
Specifications
Height: 72 metres
Length: 198 metres
Volume of RCC: 300 m3x103
Total volume: 352 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
1.10 | Traditional concrete against formwork |
Spillway
Slope | Type |
---|---|
ogee | Traditional concrete against formwork |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
Low-lime flyash (ASTM Class F) | |
Details
Country: China
Owner: -
Type: Thin Arch
Purpose(s): Hydropower
River: Qingshui
Reservoir capacity: 276 m3x106
Construction Dates
Start of Project: 01/04
Start of RCC: 01/04
End of RCC: 11/06
End of Project: -/07
Specifications
Height: 135 metres
Length: 198 metres
Volume of RCC: 550 m3x103
Total volume: 670 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
curve | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
curve | RCC against formwork (GEVR/GE-RCC) |
Spillway
Slope | Type |
---|---|
Traditional concrete against formwork |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 3000 |
Cementitious material
Cement (kg/m3) |
---|
81 |
94 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
81 | Low-lime flyash (ASTM Class F) |
94 |
Details
Country: Turkey
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Ortasui
Reservoir capacity: 18 m3x106
Construction Dates
Start of Project: -/08
Start of RCC: -/08
End of RCC: 08/10
End of Project: 09/10
Specifications
Height: 67 metres
Length: 198 metres
Volume of RCC: 157 m3x103
Total volume: 231 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
0.10 | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork |
Spillway
Slope | Type |
---|---|
0.80 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 600 |
Cementitious material
Cement (kg/m3) |
---|
125 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
0 | No pozzolan used - |
Details
Country: Brazil
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Carrero
Reservoir capacity: -
Construction Dates
Start of Project: -/10
Start of RCC: -/10
End of RCC: -/11
End of Project: -/11
Specifications
Height: 26 metres
Length: 198 metres
Volume of RCC: 32 m3x103
Total volume: 58 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Downstream
Slope | Type |
---|---|
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates