Dam Search Results
- Reservoir Capacity: 14 m3x106
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
Kodama | Japan | F W | Kodama | 14 | 10/89 | 05/91 | 12/93 | 03/97 | 102 | 280 | 358 | 570 | V 0.20 | (1) (1) | 0.76 | (1) | 0.76 | (1) | 250 | 750 | 91 | 36 | (S) | |
Toker | Eritrea | W | Toker | 14 | 11/96 | 02/98 | 05/99 | 08/99 | 73 | 263 | 187 | 210 | V | (1) | 0.80 | (1)* | 0.80 | (12)* | 330 | 330 | 110 | 85 | (F) | |
Amata | Mexico | I | San Lorenzo | 14 | 11/03 | 11/04 | 04/05 | 06/05 | 30 | 218 | 42 | 60 | V 1.00 | (8) | 1.00 | (3)* | 1.00 | (12) | 300 | 300 | 120 | 0 | (-) - | |
Qilinguan [A] | China | H | Nanhe | 14 | - /05 | - /06 | - /07 | - /08 | 77 | 140 | 45 | 55 | ||||||||||||
Dr Victor Baptista Adami (formerly Passos Maia) | Brazil | H | Chapecó | 14 | - /09 | - /10 | - /11 | 09/12 | 34 | 66 | 72 | 18 | (N) | |||||||||||
Akköy II (Aladereçam) | Turkey | H | Karaovacik | 14 | - /07 | 05/11 | 09/12 | - /13 | 60 | 260 | 226 | 306 | V | (1) | 0.80 | (1) | 0.80 | (12) | 300 | 300 | 85 | 85 | (N) | |
Xinchanghe | China | Xinchanghe | 14 | - /13 | - /14 | - /15 | - /16 | 57 | 145 | |||||||||||||||
Yunhe | China | H | Dangjiahe | 14 | - /14 | - /15 | - /16 | - /17 | 68 | 176 | ||||||||||||||
Minas San Francisco | Ecuador | H | Jubones | 14 | - /12 | - /14 | - /17 | 08/18 | 78 | 209 | 300 | 300 |
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: Japan
Owner: -
Type: Gravity
Purpose(s): Flood Control / Water Supply
River: Kodama
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: 10/89
Start of RCC: 10/89
End of RCC: 12/93
End of Project: 03/97
Specifications
Height: 102 metres
Length: 280 metres
Volume of RCC: 358 m3x103
Total volume: 570 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | Traditional concrete against formwork |
0.20 | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
0.76 | Traditional concrete against formwork |
Spillway
Slope | Type |
---|---|
0.76 | Traditional concrete against formwork |
Placement
Layers (mm) | Lifts (mm) |
---|---|
250 | 750 |
Cementitious material
Cement (kg/m3) |
---|
91 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
36 | Ground-granulated blast-furnace slag |
Details
Country: Eritrea
Owner: -
Type: Gravity
Purpose(s): Water Supply
River: Toker
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: 11/96
Start of RCC: 11/96
End of RCC: 05/99
End of Project: 08/99
Specifications
Height: 73 metres
Length: 263 metres
Volume of RCC: 187 m3x103
Total volume: 210 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
0.80 | Reinforced conventional concrete cast after RCC placement [stepped face] |
Placement
Layers (mm) | Lifts (mm) |
---|---|
330 | 330 |
Cementitious material
Cement (kg/m3) |
---|
110 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
85 | Low-lime flyash (ASTM Class F) |
Details
Country: Mexico
Owner: -
Type: Gravity
Purpose(s): Irrigation
River: San Lorenzo
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: 11/03
Start of RCC: 11/03
End of RCC: 04/05
End of Project: 06/05
Specifications
Height: 30 metres
Length: 218 metres
Volume of RCC: 42 m3x103
Total volume: 60 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against precast concrete panels with geomembrane |
1.00 |
Downstream
Slope | Type |
---|---|
1.00 | RCC against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
1.00 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
120 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
0 | No pozzolan used - |
Details
Country: China
Owner: -
Type: Thin Arch
Purpose(s): Hydropower
River: Nanhe
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: -/05
Start of RCC: -/05
End of RCC: -/07
End of Project: -/08
Specifications
Height: 77 metres
Length: 140 metres
Volume of RCC: 45 m3x103
Total volume: 55 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Downstream
Slope | Type |
---|---|
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
Details
Country: Brazil
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Chapecó
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: -/09
Start of RCC: -/09
End of RCC: -/11
End of Project: 09/12
Specifications
Height: 34 metres
Length: -
Volume of RCC: 66 m3x103
Total volume: -
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Downstream
Slope | Type |
---|---|
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
Cementitious material
Cement (kg/m3) |
---|
72 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
18 | Natural pozzolan (ASTM Class N) |
Details
Country: Turkey
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Karaovacik
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: -/07
Start of RCC: -/07
End of RCC: 09/12
End of Project: -/13
Specifications
Height: 60 metres
Length: 260 metres
Volume of RCC: 226 m3x103
Total volume: 306 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | Traditional concrete against formwork |
Downstream
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork |
Spillway
Slope | Type |
---|---|
0.80 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
85 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
85 | Natural pozzolan (ASTM Class N) |
Details
Country: China
Owner: -
Type: Gravity
Purpose(s): unknown
River: Xinchanghe
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: -/13
Start of RCC: -/13
End of RCC: -/15
End of Project: -/16
Specifications
Height: 57 metres
Length: 145 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Downstream
Slope | Type |
---|---|
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
Details
Country: China
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Dangjiahe
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: -/14
Start of RCC: -/14
End of RCC: -/16
End of Project: -/17
Specifications
Height: 68 metres
Length: 176 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Downstream
Slope | Type |
---|---|
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
Details
Country: Ecuador
Owner: -
Type: Gravity
Purpose(s): Hydropower
River: Jubones
Reservoir capacity: 14 m3x106
Construction Dates
Start of Project: -/12
Start of RCC: -/12
End of RCC: -/17
End of Project: 08/18
Specifications
Height: 78 metres
Length: 209 metres
Volume of RCC: -
Total volume: -
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Downstream
Slope | Type |
---|---|
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates