Dam Search Results
- Reservoir Capacity: 73 m3x106
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
← Scroll the table horizontally to view its entire width →
Name | Country | Owner | Purpose | River | Reservoir capacity (m3x106) | Construction dates | Dimensions | Volume | Facings | Placement | Cementitious material | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Start | Finish | Height | Length | RCC | Total | Upstream | Downstream | Spillway | Layers | Lifts | Cement | Pozzolan | ||||||||||||
Project | RCC | RCC | Project | (m) | (m) | (m3x103) | (m3x103) | Slope | Type | Slope | Type | Slope | Type | (m) | (m) | (kg/m3) | (kg/m3) | |||||||
Mae Suai | Thailand | I | Mae Suai | 73 | 11/99 | 10/00 | 01/02 | 07/02 | 59 | 340 | 300 | 350 | 0.15 | (15) | 0.80 | (1)* | 0.80 | (1)* | 300 | 300 | 70 | 80 to 100 | (F) | |
Köroglu Kotanli 1 [A-G] | Turkey | H | Kura | 73 | 03/15 | 06/15 | 02/17 | 04/17 | 100 | 404 | 640 | 680 | V | (3') | 0.60 | (3')* | 0.60 | (12) | 300 | 300 | 85 | 130 | (N) |
← Scroll the table horizontally to view its entire width →
Search again
Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.
Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.
Details
Country: Thailand
Owner: -
Type: Gravity
Purpose(s): Irrigation
River: Mae Suai
Reservoir capacity: 73 m3x106
Construction Dates
Start of Project: 11/99
Start of RCC: 11/99
End of RCC: 01/02
End of Project: 07/02
Specifications
Height: 59 metres
Length: 340 metres
Volume of RCC: 300 m3x103
Total volume: 350 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
0.15 | RCC supported by fill shoulders |
Downstream
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork [stepped face] |
Spillway
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork [stepped face] |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
70 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
80 to | Low-lime flyash (ASTM Class F) |
Details
Country: Turkey
Owner: -
Type: Arch-Gravity
Purpose(s): Hydropower
River: Kura
Reservoir capacity: 73 m3x106
Construction Dates
Start of Project: 03/15
Start of RCC: 03/15
End of RCC: 02/17
End of Project: 04/17
Specifications
Height: 100 metres
Length: 404 metres
Volume of RCC: 640 m3x103
Total volume: 680 m3x103
Construction Methods
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.60 | RCC against formwork (GEVR/GE-RCC) [stepped face] |
Spillway
Slope | Type |
---|---|
0.60 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
85 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
130 | Natural pozzolan (ASTM Class N) |
Search again
Please note: only dams with known co-ordinates will appear on this map.
Your search returned no dams with known co-ordinates