Big Cherry

Download PDF data sheet
Big Cherry completed
Big Cherry completed

Particulars

Owner: unknown

Designer: Dewberry & Davis, GEI Consultants & Kleinfelder

Contractor: Estes Brothers Construction

Statistics

Type: Gravity

Purpose(s): Water Supply

Reservoir capacity: 2 m3x106

Height: 26 metres

Length: 113 metres

Volume of RCC: 11 m3x103

Total volume: 12 m3x103

Construction Dates

Start of Project: 04/04 (April 2004)

Start of RCC: 09/04 (September 2004)

End of RCC: 01/05 (January 2005)

End of Project: 07/05 (July 2005)

Country: USA

River: South Fork, Powell River

DMS Co-ordinates: 36˚50'47.00"N, 82˚40'19.84"W

DD Co-ordinates: 36.84639, -82.67218

Facings

Upstream

SlopeType
  

Downstream

SlopeType
  

Spillway

SlopeType
  

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
82
Pozzolan (kg/m3)Pozzolan Type
82Low-lime flyash (ASTM Class F)