Leidatan
Download PDF data sheet
Particulars
Owner: unknown
Designer: Insitute of Investigation and Design for Hydropower Projects, Kunming, Yunnan Province
Contractor: 8th Construction Bureau
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 94 m3x106
Height: 84 metres
Length: 202 metres
Volume of RCC: 240 m3x103
Total volume: 340 m3x103
Construction Dates
Start of Project: 03/03 (March 2003)
Start of RCC: —/05 (— 2005)
End of RCC: —/06 (— 2006)
End of Project: 06/07 (June 2007)
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.70 | RCC against formwork (GEVR/GE-RCC) |
Spillway
Slope | Type |
---|---|
0.70 | Traditional concrete against formwork |
Placement
Layers (mm) | Lifts (mm) |
---|---|
Cementitious material
Cement (kg/m3) |
---|
Pozzolan (kg/m3) | Pozzolan Type |
---|---|