Mwache

Download PDF data sheet
Mwache under construction
Mwache under construction

Particulars

Owner: Ministry of Water and Sanitation

Designer: Nippon Koei in association with Mangat I.B. Patel

Contractor: SinoHydro (Construction Bureau Nº15)

Statistics

Type: Gravity

Purpose(s): Irrigation / Water Supply

Reservoir capacity: 136 m3x106

Height: 84 metres

Length: 526 metres

Volume of RCC: 610 m3x103

Total volume: 620 m3x103

Construction Dates

Start of Project: 04/22 (April 2022)

Start of RCC: 03/25 (March 2025)

End of RCC: 06/26 (June 2026)

End of Project: /26 ( 2026)

Country: Kenya

River: Mwache

DMS Co-ordinates: 3˚59'27.6"S, 39˚31'14.5"E

DD Co-ordinates: -3.991, 39.520695

Facings

Upstream

SlopeType
  

Downstream

SlopeType
 RCC against formwork (GEVR/GE-RCC)  [stepped face]

Spillway

SlopeType
  

Placement

Layers (mm)Lifts (mm)
300300

Cementitious material

Cement (kg/m3)
70
Pozzolan (kg/m3)Pozzolan Type
150