Upper Paung Laung
Download PDF data sheet
Upper Paung Laung completed

Particulars
Owner: unknown
Designer: AF-Colenco Ltd.
Contractor: DHPI, HTCT, MSP, YMEC
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 1300 m3x106
Height: 103 metres
Length: 530 metres
Volume of RCC: 936 m3x103
Total volume: 1100 m3x103
Construction Dates
Start of Project: 01/06 (January 2006)
Start of RCC: 01/11 (January 2011)
End of RCC: 12/13 (December 2013)
End of Project: —/14 (— 2014)
Country: Myanmar
River: Paung Laung
DMS Co-ordinates: 19˚45'22.59"N, 96˚35'37.3"E
DD Co-ordinates: 19.756275, 96.593697
Facings
Upstream
| Slope | Type |
|---|---|
| Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
| Slope | Type |
|---|---|
| 0.80 | RCC against formwork (GEVR/GE-RCC) [stepped face] |
Spillway
| Slope | Type |
|---|---|
| 0.80 | Reinforced conventional concrete cast after RCC placement |
Placement
| Layers (mm) | Lifts (mm) |
|---|---|
| 300 | 300 |
Cementitious material
| Cement (kg/m3) |
|---|
| 90 |
| Pozzolan (kg/m3) | Pozzolan Type |
|---|---|
| 140 | Natural pozzolan (ASTM Class N) |