Wanmipo
Download PDF data sheet
Particulars
Owner: unknown
Designer: Mid-South China Insitute of Investigation, Design and Research for Hydropower Projects
Contractor: 7th Construction Bureau
Statistics
Type: Gravity
Purpose(s): Hydropower / Navigation
Reservoir capacity: 378 m3x106
Height: 65 metres
Length: 238 metres
Volume of RCC: 141 m3x103
Total volume: 376 m3x103
Construction Dates
Start of Project: 08/01 (August 2001)
Start of RCC: 11/02 (November 2002)
End of RCC: 05/03 (May 2003)
End of Project: 05/04 (May 2004)
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.75 | Reinforced conventional concrete cast after RCC placement |
Spillway
Slope | Type |
---|---|
ogee | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 3000 |
Cementitious material
Cement (kg/m3) |
---|
86 |
68 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
103 | Low-lime flyash (ASTM Class F) |
83 |