Dam Search Results

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the table below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

← Scroll the table horizontally to view its entire width →

NameCountryOwnerPurposeRiverReservoir capacity (m3x106)Construction datesDimensionsVolumeFacingsPlacementCementitious material
StartFinishHeightLengthRCCTotalUpstreamDownstreamSpillwayLayersLiftsCementPozzolan
ProjectRCCRCCProject(m)(m)(m3x103)(m3x103)SlopeTypeSlopeTypeSlopeType(m)(m)(kg/m3)(kg/m3)
TakizawaJapanF N WNakatu6303/9910/0106/0303/0713942481016700.15
0.70
(1)
(1)
0.72(1)0.72(1)250100084
72
36
48
(F)
BureyaRussiaF HBureya2100001/7601/85- /03- /091398107093538V(1)0.70(1)0.70(1)300 -
500
300 -
500
95 to  11025 to  30(N)
Yunlonghe Nº3
[A]
ChinaHYunlong4403/0604/0704/09- /11139119182207curve(3')curve(3') (3')     

← Scroll the table horizontally to view its entire width →

 

Search again

Please note: only dams ≥ 15m which have been completed, are under construction, or due to begin RCC placement in the current year are included in the list below.

Results are sorted in the following order: Finish of RCC, Start of RCC, Finish of Project, Start of Project, Height and alphabetical by Dam Name.

Full Dam Information

Details

Country: Japan

Owner: -

Type: Gravity

Purpose(s): Flood Control / Navigation / Water Supply

River: Nakatu

Reservoir capacity: 63 m3x106

Construction Dates

Start of Project: 03/99

Start of RCC: 03/99

End of RCC: 06/03

End of Project: 03/07

Specifications

Height: 139 metres

Length: 424 metres

Volume of RCC: 810 m3x103

Total volume: 1670 m3x103

Construction Methods

Facings

Upstream
SlopeType
0.15Traditional concrete against formwork
0.70Traditional concrete against formwork
Downstream
SlopeType
0.72Traditional concrete against formwork
Spillway
SlopeType
0.72Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
2501000

Cementitious material

Cement (kg/m3)
84
72
Pozzolan (kg/m3)Pozzolan Type
36Low-lime flyash (ASTM Class F)
48 
Takizawa completed
Takizawa completed

Full Dam Information

Details

Country: Russia

Owner: -

Type: Gravity

Purpose(s): Flood Control / Hydropower

River: Bureya

Reservoir capacity: 21000 m3x106

Construction Dates

Start of Project: 01/76

Start of RCC: 01/76

End of RCC: -/03

End of Project: -/09

Specifications

Height: 139 metres

Length: 810 metres

Volume of RCC: 709 m3x103

Total volume: 3538 m3x103

Construction Methods

Facings

Upstream
SlopeType
VerticalTraditional concrete against formwork
Downstream
SlopeType
0.70Traditional concrete against formwork
Spillway
SlopeType
0.70Traditional concrete against formwork

Placement

Layers (mm)Lifts (mm)
300  -300  -
500500

Cementitious material

Cement (kg/m3)
95  to
Pozzolan (kg/m3)Pozzolan Type
25  toNatural pozzolan (ASTM Class N)
  
Bureya completed
Bureya completed

Full Dam Information

Details

Country: China

Owner: -

Type: Thin Arch

Purpose(s): Hydropower

River: Yunlong

Reservoir capacity: 44 m3x106

Construction Dates

Start of Project: 03/06

Start of RCC: 03/06

End of RCC: 04/09

End of Project: -/11

Specifications

Height: 139 metres

Length: 119 metres

Volume of RCC: 182 m3x103

Total volume: 207 m3x103

Construction Methods

Facings

Upstream
SlopeType
curveRCC against formwork (GEVR/GE-RCC)
Downstream
SlopeType
curveRCC against formwork (GEVR/GE-RCC)
Spillway
SlopeType
 RCC against formwork (GEVR/GE-RCC)

Placement

Layers (mm)Lifts (mm)
  

Cementitious material

Cement (kg/m3)
 
Pozzolan (kg/m3)Pozzolan Type
  
  
Yunlonghe Nº3 completed
Yunlonghe Nº3 completed

 

Search again