Asagi (Lower) Kaleköy
Download PDF data sheet
Particulars
Owner: unknown
Designer: unknown
Contractor: unknown
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 556 m3x106
Height: 125 metres
Length: 346 metres
Volume of RCC: 1192 m3x103
Total volume: 1342 m3x103
Construction Dates
Start of Project: 03/13 (March 2013)
Start of RCC: —/15 (— 2015)
End of RCC: —/20 (— 2020)
End of Project: 04/21 (April 2021)
Country: Turkey
River: Murat
DMS Co-ordinates: 38˚49'51.45"N, 40˚42'33.09"E
DD Co-ordinates: 38.830833, 40.70919
Facings
Upstream
Slope | Type |
---|---|
0.25 | RCC against precast concrete panels |
Downstream
Slope | Type |
---|---|
0.80 | RCC against formwork |
Spillway
Slope | Type |
---|---|
separate |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
90 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
40 | Milled sand |