Longtan (Stage 1)
Download PDF data sheet
Particulars
Owner: unknown
Designer: Mid-South Design Institute for Hydroelectric Projects, MOE & MWR
Contractor: JV of 7th, 8th and Gezhouba Construction Bureaux (Right Bank) and Jiangnan Co. Ltd. (Left Bank)
Statistics
Type: Gravity
Purpose(s): Flood Control / Hydropower / Navigation / Water Supply
Reservoir capacity: 16210 m3x106
Height: 192 metres
Length: 832 metres
Volume of RCC: 4623 m3x103
Total volume: 7400 m3x103
Construction Dates
Start of Project: 07/01 (July 2001)
Start of RCC: 10/04 (October 2004)
End of RCC: 06/07 (June 2007)
End of Project: 12/09 (December 2009)
Country: China
River: Hongshui
DMS Co-ordinates: 25˚01'41.99"N, 107˚02'36.40"E
DD Co-ordinates: 25.028332, 107.043442
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
0.25 |
Downstream
Slope | Type |
---|---|
0.70 | RCC against formwork (GEVR/GE-RCC) |
Spillway
Slope | Type |
---|---|
0.68 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
99 |
86 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
121 | Low-lime flyash (ASTM Class F) |
109 |