Murum
Download PDF data sheet
Particulars
Owner: unknown
Designer: Changjiang Survey, Planning, Design and Research Co. Ltd.
Contractor: Three Gorges Development Co
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 12043 m3x106
Height: 146 metres
Length: 440 metres
Volume of RCC: 1520 m3x103
Total volume: 1660 m3x103
Construction Dates
Start of Project: 10/08 (October 2008)
Start of RCC: 05/10 (May 2010)
End of RCC: 07/13 (July 2013)
End of Project: —/15 (— 2015)
Country: Malaysia
River: Murum
DMS Co-ordinates: 2˚38'58.25"N, 114˚22'2.57"E
DD Co-ordinates: 2.649514, 114.367378
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
0.20 | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.70 | RCC against formwork |
0.80 |
Spillway
Slope | Type |
---|---|
0.70 | |
0.80 |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 3000 |
Cementitious material
Cement (kg/m3) |
---|
88 |
65 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
88 | Low-lime flyash (ASTM Class F) |
72 |