Taishir

Download PDF data sheet
Taishir completed
Taishir completed

Particulars

Owner: unknown

Designer: AMEC-SMEC Joint Venture

Contractor: SinoHydro Co. Ltd.

Statistics

Type: Gravity

Purpose(s): Hydropower / Irrigation / Water Supply

Reservoir capacity: 930 m3x106

Height: 60 metres

Length: 200 metres

Volume of RCC: 210 m3x103

Total volume: 250 m3x103

Construction Dates

Start of Project: 02/05 (February 2005)

Start of RCC: 05/06 (May 2006)

End of RCC: 06/07 (June 2007)

End of Project: 12/07 (December 2007)

Country: Mongolia

River: Zabkhan

DMS Co-ordinates: 46˚41'39.14"N, 96˚39'56.75"E

DD Co-ordinates: 46.694206, 96.665764

Facings

Upstream

SlopeType
VerticalTraditional concrete against formwork with external geomembrane

Downstream

SlopeType
0.72Traditional concrete against formwork  [stepped face]

Spillway

SlopeType
0.72Reinforced conventional concrete cast after RCC placement  [stepped face]

Placement

Layers (mm)Lifts (mm)
333333

Cementitious material

Cement (kg/m3)
75
Pozzolan (kg/m3)Pozzolan Type
0No pozzolan used  -