Tukaihe
Download PDF data sheet
Particulars
Owner: unknown
Designer: Beijing Hydropower Investigation, Design and Research Institute
Contractor: unknown
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 78 m3x106
Height: 59 metres
Length: 300 metres
Volume of RCC: 255 m3x103
Total volume: 570 m3x103
Construction Dates
Start of Project: 04/04 (April 2004)
Start of RCC: 12/05 (December 2005)
End of RCC: —/06 (— 2006)
End of Project: —/07 (— 2007)
Country: China
River: Lixian
DMS Co-ordinates: 22˚34'23.09"N, 102˚17'38.32"E
DD Co-ordinates: 22.57308, 102.293976
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
RCC against formwork (GEVR/GE-RCC) |
Spillway
Slope | Type |
---|---|
RCC against formwork (GEVR/GE-RCC) |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 3000 |
Cementitious material
Cement (kg/m3) |
---|
65 |
93 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
110 | Ground-granulated blast-furnace slag |
113 |