Yukari (Upper) Kalekö
Download PDF data sheet
Particulars
Owner: unknown
Designer: Temelsu International Engineering Services Inc.
Contractor: Ozaltin Ins. Tic. ve San A.S.
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 784 m3x106
Height: 150 metres
Length: 516 metres
Volume of RCC: 2224 m3x103
Total volume: 2414 m3x103
Construction Dates
Start of Project: 06/12 (June 2012)
Start of RCC: 06/14 (June 2014)
End of RCC: 09/16 (September 2016)
End of Project: 04/18 (April 2018)
Country: Turkey
River: Murat
DMS Co-ordinates: 38˚48'49.70"N, 41˚2'31.55"E
DD Co-ordinates: 38.813889, 41.042095
Facings
Upstream
Slope | Type |
---|---|
0.25 | RCC against precast concrete panels |
Downstream
Slope | Type |
---|---|
0.80 | Traditional concrete against formwork |
Spillway
Slope | Type |
---|---|
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
90 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
40 | Milled sand |