Hongpo
Download PDF data sheet
Particulars
Owner: unknown
Designer: Insitute of Investigation and Design of Water Resources and Hydropower, Kunming City
Contractor: 8th Construction Bureau, MOE & MWR
Statistics
Type: Arch-Gravity
Purpose(s): Water Supply
Reservoir capacity: 3 m3x106
Height: 55 metres
Length: 244 metres
Volume of RCC: 71 m3x103
Total volume: 77 m3x103
Construction Dates
Start of Project: 10/97 (October 1997)
Start of RCC: 07/98 (July 1998)
End of RCC: 11/99 (November 1999)
End of Project: 12/99 (December 1999)
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.50 | Traditional concrete against formwork |
Spillway
Slope | Type |
---|---|
0.50 | Traditional concrete against formwork |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 3000 |
Cementitious material
Cement (kg/m3) |
---|
54 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
99 | Low-lime flyash (ASTM Class F) |