Zhouning
Download PDF data sheet
Particulars
Owner: unknown
Designer: Fujian Institute of Investigation, Design and Research for Hydropower Projects, Fuzhou City
Contractor: Fujian (Minjiang) Construction Bureau
Statistics
Type: Gravity
Purpose(s): Hydropower
Reservoir capacity: 47 m3x106
Height: 73 metres
Length: 206 metres
Volume of RCC: 159 m3x103
Total volume: 199 m3x103
Construction Dates
Start of Project: —/02 (— 2002)
Start of RCC: 04/03 (April 2003)
End of RCC: 03/04 (March 2004)
End of Project: 06/04 (June 2004)
Facings
Upstream
Slope | Type |
---|---|
Vertical | RCC against formwork (GEVR/GE-RCC) |
Downstream
Slope | Type |
---|---|
0.72 | RCC against formwork (GEVR/GE-RCC) |
Spillway
Slope | Type |
---|---|
0.70 | Reinforced conventional concrete cast after RCC placement |
Placement
Layers (mm) | Lifts (mm) |
---|---|
300 | 300 |
Cementitious material
Cement (kg/m3) |
---|
67 |
50 |
Pozzolan (kg/m3) | Pozzolan Type |
---|---|
100 | Low-lime flyash (ASTM Class F) |
92 |